SembCorp Marine@12
Sembcorp Marine Ltd, through its wholly owned subsidiary, Estaleiro Jurong Aracruz (EJA), has secured an
Amendment Contract from Tupi B.V. valued at about USD175 million (approximately SGD230 million) for
modification work to be completed on the Floating Production Storage and Offloading (FPSO) P-71 oil and gas vessel.
Originally designed for the Tupi field, the FPSO P-71 will undergo modification and integration at EJA for deployment at the Itapu field.
This Project provides an opportunity to showcase EJA’s capabilities to undertake
large scale and complex engineering projects with
quick design adaptation and superior subsea layout
Amid the pandemic-induced challenges, we remain committed to the
safe and timely execution of the project.
https://links.sgx.com/FileOpen/Annouceme...eID=673223
Stay home and stay safe, everyone.
When I read this news, all the key words for project failure came into my mine. What was management of SembCorp Marine thinking?
1) Originally designed for Tupi field and now need to modify to cater for Itapu field - had they consider the extends of the modification needed?
2) Yes, they sure did. This is going to be a
large scale and complex project.
3) ok. if this is the case, ample time will be given for the changes, right?
I doubt so, first, the design phase is cut short - see they use the word
"quick design"?
Then see the word
"timely execution" which means that need to squeeze implementation time (other than squeezing design time) too.